Large Structure Checklist

It’s the customer’s responsibility to check town requirements!

  • This is generally on average a 6-month process
  • Drawings, 1 month. Regular drawings take about 2-4 weeks and cost 500.00.   Sealed/stamped drawings cost 1000.00 and take 4-6 weeks
  • Township approval, 1-2 months. Once you have your drawings, please submit them to the town for Final approval.
  • Foundation, 1-2 months. We do not do the foundation but work with different companies based on your needs and location. Please ask for foundation contact information from your sales rep
  • Foundation is done, Build process 2-3 months. Once the foundation is done please contact us as we like to take final measurements to ensure a proper installation. Once the measurements are sent over, we should have a rough install date.
  • Please note, there is nothing we can do to expedite orders or drawings.
  • Drawings are a separate cost and an order for drawings needs to be in place to receive them.

 

Suggested Foundations

Check town requirements for foundation

Screen-Shot-2021-12-02-at-10.27.25-AM-300x254

Frost Protected Foundation

  • 8″ off of ground contact adding to the longevity 
  • Most towns will require this foundation

 

Screen-Shot-2021-12-02-at-10.27.07-AM-1024x119

Haunch Foundation

  • Simplest foundation to do
  • Some towns will allow this
Amish Mike- Amish Sheds, Amish Barns, Sheds NJ, Sheds, Barns
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.